PMO Dashboard
Portfolio Progress
68%
+5% vs last week
Projects
57
49 active, 8 inactive
Activities
54,968
24,718 with UDF weights
BAC
SAR 5.05B
Budget at completion
Open Issues
17
4 critical, 13 minor
Overdue Tasks
23
Requiring attention
Workstream Progress
Backend API89%
Frontend UI72%
QA & Testing54%
Data Migration38%
Infrastructure95%
Active Tasks
DB schema migration script
A. Hassan
OverdueAuth service integration
S. Patel
In reviewDashboard UI redesign
L. Kim
In progressCI/CD pipeline setup
M. Torres
DoneLoad testing report
R. Chen
BlockedAPI rate limiter config
T. Nguyen
In reviewEPS Groups
Prof01 — 29 projects71%
Prof02 — 9 projects58%
Prof03 — 5 projects44%
Prof04 — 9 projects32%
Upcoming Milestones
Data migration complete
Apr 12UAT start
Apr 21Security pentest
May 28UAT sign-off
May 30Staging deployment
Jun 4Production go-live
Jun 11BAC
SAR 5.05B
Budget at completion
BCWP
SAR 2.84B
Earned value
BCWS
SAR 4.16B
Planned value
SPI
0.684
Schedule behind plan
CPI
0.910
Cost slightly under
EAC
SAR 5.55B
Estimate at completion
Full EV Metrics
BAC — Budget at completion
SAR 5,050M
BaselineBCWP — Earned value
SAR 2,840M
56.2%BCWS — Planned value
SAR 4,160M
82.4%SPI — Schedule perf. index
0.684
BehindCPI — Cost perf. index
0.910
WatchEAC — Estimate at completion
SAR 5,549M
+SAR 499METC — Estimate to complete
SAR 2,709M
RemainingCV — Cost variance
−SAR 499M
OverSV — Schedule variance
−SAR 1,320M
BehindHealth by EPS Group
Prof01
SPI 0.71
29 projects — Amber health
Prof02
SPI 0.96
9 projects — Green health
Prof03
SPI 0.61
5 projects — Red health
Prof04
SPI 0.82
9 projects — Amber health
High Risks
2
Immediate action needed
Medium Risks
3
Monitor closely
Low Risks
4
Under control
Data migration delay
HighScript 3 weeks behind. Risks missing UAT window entirely.
Payment gateway SLA
HighThird-party SLA unconfirmed for go-live. Blocking dependency.
Team capacity gap
MediumTwo senior engineers on leave in May. Backfill still pending.
Scope creep
MediumStakeholder additions outside PRD increasing backlog.
SPI below 0.7 trend
MediumPortfolio SPI 0.684. If drops below 0.65 escalation required.
QA tool license
LowLicense renewal due May 15. Procurement notified.
Security audit timing
LowPentest May 28. Findings may cause minor launch delay.
Bridge agent downtime
LowVM dependency — no failover if VM goes offline during sync.
Supabase local → prod
LowMust migrate before app store launch. No blocker yet.
Probability vs Impact Matrix
Impact ↑
Low
Rare
Low
Unlikely
Med
Possible
High
Likely
V.High
Almost
Data Mig ●
SPI ●
Scope ●
Gateway ●
Capacity ●
RareUnlikelyPossibleLikelyAlmost certain
Probability →
Urgent Decisions
2
Due this week
Pending Review
3
Awaiting response
Resolved Today
0
Logged below
Approve emergency contractor hire
Due Apr 7
Data migration at risk — 2 contractors for 6 weeks requested to close the gap before UAT.
Defer payment gateway feature to v1.1
Due Apr 10
Recommend pushing advanced billing UI to de-risk go-live. Impacts 3 dependent screens.
Extend UAT window by 1 week
Due Apr 14
QA team requesting extra time given current backlog. Pushes go-live from Jun 4 to Jun 11.
Confirm go-live date with client
Due Apr 18
Client needs official Jun 11 confirmation to plan their internal rollout and training.
Approve WBS hierarchy scope addition
Due Apr 21
6-level WBS tree requires schema migration + bridge agent update. 3 days effort estimated.
Decision Log
No decisions recorded yet.