Project Delivery Readiness Model (PDRM)


Project Delivery Readiness Model (PDRM)

How to use this page:
Use the left-side menu to navigate through the readiness domains. Expand any section by clicking on it. At the end, use the Readiness Calculator to enter scores (0–10) for each domain and obtain the overall Project Delivery Readiness rating.


Overview

Why Projects Fail

Owner weak readiness, contractor capability gaps, external misalignment, and internal project LEGO gaps (team, scope, design, procurement, schedule, cost, risk, site, contract).

Purpose of PDRM

Define what “ready to deliver” means, set a benchmark, and enforce minimum thresholds before moving from planning to execution.

Framework Overview

The readiness model evaluates five domains: Owner (30%), Contractor (25%), Project LEGO (25%), External Parties (10%), and Project Management Envelope (10%).

Scoring Logic

Each domain is scored 0–10. Scores are weighted and combined into an overall readiness percentage. Green ≥ 70%, Amber 50–69%, Red < 50%.

Owner Readiness (30% Weight)

Owner Summary

Measures the owner’s governance, PMO strength, funding certainty, processes, and internal capability to sponsor and steer the project.

Governance Maturity

Clarity of organizational structure, delegation of authority, steering committee effectiveness, escalation paths, and PMO authority over baselines and changes.

Capability & Experience

Availability and experience of project sponsors, project managers, planners, controllers, and subject-matter experts across similar projects and portfolios.

Funding Readiness

Budget approval status, multi-year funding visibility, cash flow planning, contingency allocation, and discipline in variation approvals.

Process & Controls

Presence and application of baseline approval procedures, change control, contract administration, risk management, and reporting standards.

Contractor Readiness (25% Weight)

Contractor Summary

Assesses the main contractor’s financial strength, technical capability, planning and controls maturity, and track record.

Financial Strength

Liquidity, backlog balance, credit lines, bonding capacity, insurance coverage, and exposure to claims or disputes.

Technical Capability

Quality and stability of key staff (PM, construction manager, planner, QS, QA/QC, HSE), engineering depth, and access to specialist subcontractors.

Planning & Controls

Use of Primavera or equivalent tools, schedule quality, forecasting capability, cost control, and integration between time, cost, and risk.

Past Performance

Safety performance, quality of deliverables, history of delays, change orders, and claim severity on previous similar projects.

Project LEGO Readiness (25% Weight)

LEGO Overview

Evaluates whether the core building blocks of delivery (team, scope, design, procurement, schedule, cost, risk, site, contract) are ready and aligned.

Team LEGO

Key roles defined and filled (client, consultant, contractor), competency level, capacity, and clarity of RACI across disciplines.

Scope LEGO

Complete and structured WBS, clear scope boundaries and interfaces, documented assumptions, and alignment with the business case.

Design LEGO

Design status (concept, detailed, IFC), level of coordination between disciplines, VE decisions, and design review/approval status.

Procurement LEGO

Identification of long-lead items, procurement strategy, prequalification of suppliers, contract packaging, and tender/award status.

Schedule LEGO

Presence of an integrated baseline, critical path clarity, links to design and procurement, realistic durations, and resource/loading view.

Cost, Risk, Site & Contract

Approved budget and contingency, risk register and mitigations, site access and constraints, and clarity of contract terms and risk allocation.

External Parties Readiness (10% Weight)

Regulatory Readiness

Permits, NOCs, environmental approvals, and alignment with regulatory timelines and conditions.

Stakeholder Influence

Identification and mapping of external stakeholders, their power/interest, and an engagement plan to manage resistance.

End-User Readiness

Defined acceptance criteria, commissioning and handover requirements, and readiness of operations/maintenance teams to receive the asset.

Project Management Envelope (10% Weight)

Market Conditions

Inflation trends, labor market tightness, material price volatility, and currency risks that affect project viability.

Political & Legal Environment

Political stability, contract law enforcement, dispute resolution mechanisms, and regulatory transparency.

Industry & Supply Chain

Sector complexity, availability of specialized suppliers, logistics constraints, and dependency on imported technologies.

Critical Rules

Trigger Conditions (The project must calculate all risk if Any of these are TRUE)
  • Funding is not fully approved or secured.
  • Land or site is not handed over and accessible.
  • Key permits or regulatory approvals are missing.
  • Key owner or contractor roles are unfilled.
  • No approved integrated baseline schedule exists.
  • No documented procurement strategy and LLIs plan.
  • Design is not sufficiently developed (no IFC where needed).

Readiness Score Calculator

Enter ratings (0–10) to calculate weighted readiness for each domain.

Owner (30%)
Score: / 10
Contractor (25%)
Score: / 10
Project LEGO (25%)
Score: / 10
External Parties (10%)
Score: / 10
Project Management Envelope (10%)
Score: / 10

Overall Readiness Score:

Green ≥ 70%, Amber 50–69%, Red < 50%

error: Content is protected !!